Dokaflex 124 Soffit Support System Installation Guide

How to erect and strike the Dokaflex 124 Soffit Support System, the hand-set timber-beam falsework we hire for concrete slabs and soffits.

You start from a corner, erecting Eurex 30 Props with Tripods and Lowering Heads on a grid, then add the H20 Primary beams, intermediate props, H20 Secondary beams and a plywood deck. The layout table below gives prop and beam spacings for slabs up to 0.50m thick. To strike the system, you work from below the deck on a suitable moveable scaffolding tower, remove the intermediate props and then hit the Lowering Heads with a hammer, which drops the entire deck. This guide also covers lateral restraint, drop beams and slab edges.

If you'd like a printable copy, download the Dokaflex User Guide (PDF). For full specifications, see the Dokaflex 124 Soffit Support System product page.

Dokaflex Component Weights

ItemWeight
Eurex 30 Prop (2.50m)14.8kg
Eurex 30 Prop (3.0m)16.7kg
Eurex 30 Prop (3.5m)20.5kg
1.80m H20 Beam9.5kg
2.65m H20 Beam14.1kg
2.90m H20 Beam15.4kg
3.30m H20 Beam17.5kg
3.90m H20 Beam20.7kg
5.90m H20 Beam31.3kg
Tripod15.6kg
Lowering Head6.1kg
Supporting Head0.77kg
Slab ThicknessUp to 0.30m0.35m0.40m0.45m0.50m
Applied Load9.66kN/m²11.22kN/m²12.78kN/m²14.34kN/m²15.9kN/m²
Secondary Beam Spacing0.50m0.45m0.40m0.40m0.40m
Primary Beam Spacing2.00m2.00m2.00m1.75m1.50m
Prop Spacing1.00m1.00m0.75m0.75m0.75m

For slab thicknesses greater than 0.50m, please contact SEL for advice.

Installation Sequence

1. Erect the props

Eurex 30 Props with Foldable Tripods and Lowering Heads standing on a 2m by 3m grid inside a walled area

Starting from a corner, erect Eurex 30 Props with Tripod support on a grid of 2m by 3m (for slabs up to 300mm thick; for thicker slabs see 'Recommended System Layouts' table for closer prop spacings).

Equip each Eurex 30 Prop with a Lowering Head in the open (taller) position.

Set prop height (inc. head) to be 418mm less than the soffit height. Adjust for the plywood deck thickness (18mm assumed).

Edge props to be max. 500mm from the surrounding walls.

2. Install the primary beams

Three lines of 200mm deep H20 Primary Beams on the Lowering Heads, 2m apart, with intermediate props with Supporting Heads at 1m centres along each line

Install the 3.9m Primary H20 timber beams between Lowering Heads, leaving an equal overhang on each end of the beams.

Erect the intermediate supporting props at 1m centres and equip with Supporting Heads.

3. Install the secondary beams

200mm deep H20 Secondary Beams laid at close, regular centres across the Primary Beams, covering the whole area

Install the 2.65m H20 Secondary beams at 0.5m (one mark) centres (see adjacent table for closer secondary spacings for slabs over 300mm thick).

Install H20 Securing Clips at the intersection of every Secondary and Primary beam above the prop locations.

At column locations, place H20 Secondary beams either side of the column and install additional supporting timber where the gap exceeds 0.50m. Secure the plywood deck around the column with additional timber where required.

4. Install the deck and edge protection

Plywood decking laid across most of the Secondary Beams, with the beams still exposed along one side and at one end

Install suitable decking plywood (not supplied by SEL).

Suitable edge protection must be installed on all sides of the deck where required. Site Equipment's Edge Safe barrier system can be installed on both Primary and Secondary beams with accompanying barriers.

Close-up of mesh edge protection barriers on posts clamped to the Secondary Beams along the edge of the plywood deck

Lateral Restraint

Push/Pull props fixed to H20 beams with Washer Plates and Wing Nuts, with an H20 Securing Clip at the beam intersection above a prop

The Dokaflex system is designed as a 'Top Restrained System'. The primary method of providing lateral restraint is to install the decking tight against completely surrounding walls and internal columns.

Where this is not possible, Push/Pull props can be secured to the Primary and/or Secondary H20 beams using tie bar, washer plates and wing nuts.

Striking the System

Two views of a Lowering Head under an H20 beam: an arrow showing where to strike the Lowering Head, then the head collapsed with an arrow showing the system dropping down

The entire system should be removed from below the deck, utilising a suitable moveable scaffolding tower.

  1. Remove all intermediate props (with Supporting Heads) and H20 Securing Clips.
  2. Lower the Dokaflex deck by striking the Lowering Heads with a hammer. The entire deck will drop down.
  3. Turn the Secondary beams onto their sides and remove. Leave all Secondary beams below plywood deck joints in place.
  4. Remove plywood deck panels.
  5. Remove remaining Secondary beams and all Primary beams.
  6. Remove all Foldable Tripods and remaining props (with Lowering Heads).

NB: Stipulated striking times must be managed by the Contractor.

Drop Beams & Slab Edges

Section through a Dokaflex deck with a lower deck at each side for drop beam formwork, Push/Pull props, scaffold lacing between props, and a cantilevered primary beam projecting over the slab edge

Drop beams can be accommodated using the Dokaflex system by incorporating a lower deck upon which the main slab deck can sit.

Working room can be allowed to the side of the slab allowing for the drop beam formwork to be installed. Lateral restraint in both directions must be provided.

For the upper levels, the slab edge 'Table' must utilise a longer cantilevered Primary beam which is tied down to the main floor slab using Push/Pull props to ensure stability.

Depending on the geometry and overhang required, the Primary beams may need to be twinned to ensure adequate strength.

We can help with your next project.

Our team is friendly, knowledgeable and ready to consult. We offer no-obligation site visits, fast delivery and competitive rates. Simply fill in the form and we'll be in touch.

You can also give us a call at any time.