Double Acting Brace System Installation Guide
This is a step-by-step safe use guide covering how to assemble, install, and extract the Double Acting Brace System, SEL's modular hydraulic bracing frame for four-sided excavations such as manholes and pumping chambers. Once the legs are pinned together on timber bearers and pumped out to size, the frames are lifted into position using an excavator or crane and a 4-leg chain sling to brace perimeter trench sheets using either the dig-and-push or pre-driven sheet method.
Key Considerations
- Required Plant & Lifting Equipment
- Excavator or crane · 4-leg chain sling · hydraulic pump
- Component Weights
- 260kg (Type A leg) to 627kg (Type E leg) · 1,040–2,508kg per frame
- Working Limits
- 2.00m–7.00m sheet-to-sheet · min 100mm ram extension
- Installation Methods
- Dig & push (with dummy frames) or pre-driven sheets
Installation Sequence
Step 1: Lay Out the First Brace Leg on Timber Bearers

Using an excavator or crane and a 2-leg or 4-leg chain sling hooked through the welded lifting points on the outer body, lift the first Double Acting Brace leg and lay it flat on suitable timber bearers on level ground.
If preferred—or where crane lifting capacity is restricted—the legs can be lowered individually and assembled directly within the excavation at the level specified in the Temporary Works Design by following Steps 1–2 inside the dig.
Step 2: Pin the Four Legs Together and Pump Out the Frame


Lift and lay the remaining three legs onto timber bearers to form a four-sided frame and lock each corner together by inserting a vertical 40Ø Pin & R-Clip (see a ). The frame legs are delivered fully retracted. Check that the hydraulic pump tank is filled with shoring fluid, attach the two single hydraulic hoses to either side of the pump, and connect them to the male quick-release couplings inside the housing near the end of the inner leg section. Open the isolation valves, pump out the four legs to the required external dimensions, and close the lock-off valves to hold pressure.
Pump out all four legs incrementally—moving around the frame from leg to leg—so the corners remain square and do not bind.
Monitor the shoring fluid level in the pump reservoir throughout; topping up with additional shoring fluid is normally required when extending all four legs of a complete frame.
Step 3: Excavate the Starter Pit and Lift In Two Frame Levels

Steps 3–7 describe the 'Dig & Push' installation method for an excavation with two permanent frame levels (Frame F1 upper and Frame F2 lower). For pre-driven sheets or three or more frame levels, see Alternative Installation Methods and Removal.
Locate all underground services in accordance with NRSWA regulations, then excavate a shallow starter pit down to the underside of the upper Frame F1 level (battering or stepping the perimeter edges as required).
Using an excavator or crane and a certified 4-leg chain sling attached to the dedicated lifting lugs, lower two assembled frame levels—permanent Frame F1 at the bottom with Temporary Frame A stacked above it—onto timber bearers in the starter pit.
Step 4: Pitch and Push the Perimeter Trench Sheets

Using the two stacked frames as an internal pitching template and guide, pitch trench sheets around the full perimeter of the excavation and push them down using the excavator bucket and the correct driving cap until refusal, or to approximately half the final excavation depth. Hook the frame restraint chains onto the tops of the sheets.
Shorter trench sheets may be used temporarily on one side to leave a lower digging window for the excavator arm if required.
Step 5: Excavate to Mid-Depth and Install Temporary Frame B

Excavate inside the sheets down to the midpoint between the final levels of upper Frame F1 and lower Frame F2. Install a 'dummy' Temporary Frame B at this midpoint to restrain the toe of the sheets before digging deeper.
Lower Temporary Frame B partially retracted on a 4-leg chain sling so it clears upper Frame F1, then pump it out firmly against the sheets and close its lock-off valves (or assemble it leg-by-leg inside the excavation if clearance is tight).
Once Temporary Frame B is pressurised, lift out Temporary Frame A from above Frame F1.
Step 6: Excavate to Lower Frame Level and Install Frame F2

Continue excavating and incrementally pushing the trench sheets down until you reach the underside of the lower Frame F2 level.
Lower permanent Frame F2 into position using a 4-leg chain sling, pump its legs out against the sheets, close the lock-off valves, and hook on its vertical restraint chains.
Once Frame F2 is installed and pressurised, retract and lift out Temporary Frame B from above it, then continue digging and pushing the sheets down to the final formation level (repeating the temporary frame sequence if additional lower frame levels are required).
Step 7: Push Sheets to Formation Level and Fit Edge Protection

Ensure all perimeter trench sheets are pushed down to their final design toe level (normally at or below formation level).
Fit perimeter edge protection barriers and a ladder access platform around the top of the excavation.
To extract the system by backfilling, carry out this procedure in reverse—reinstalling the temporary frame levels as needed while compacting backfill in stages so the sheets remain supported at every stage.
Alternative Installation Methods and Removal
Alternative Installation: Pre-Driven Sheets
Use the pre-driven method when ground conditions are too firm or dense to push the trench sheets down with an excavator bucket, or where the Temporary Works Design requires full sheet toe-in before excavation begins. Instead of pushing the sheets down in stages around dummy frames, drive all sheets to full depth first using a driving cap or Excavator Mounted Vibrator (EMV), then excavate and brace from the top down:
- Pre-drive all perimeter trench sheets to the final toe level specified in the Temporary Works Design using suitable plant.
- Excavate inside the sheets down to the underside of the upper Frame F1.
- Lift in and pressurise Frame F1 at the level specified in the Temporary Works Design.
- Excavate down to the underside of the lower Frame F2.
- Lift in and pressurise Frame F2 at the level specified in the Temporary Works Design.
- Excavate down to the final formation level.
- Unless a concrete base slab is poured (see Two-Stage Construction below), backfill and compact the excavation to the underside of each frame before retracting and removing it.
Dig & Push Installation with Three or More Frame Levels
Where three or more permanent frames are required, repeat Step 6 (Installing Frame F2) using additional temporary frame levels at each intermediate stage so the bottom of the sheets is restrained at all times.
Excessive sheet cantilever below the lowest frame must be avoided.
Two-Stage Construction - Casting of Concrete Base Slab
- Prepare the formation adequately to enable a concrete base slab to be poured.
- Cast a suitable concrete base slab ensuring contact with the sheet piles around the entire perimeter. Use plywood or another suitable separation membrane to enable later extraction of the sheets.
- Once the slab can sustain the load specified in the Temporary Works Design, remove the lowest frame level. Ensure the weight of the equipment is accounted for in the Contractor's Lift Plan, and keep the frame fully supported by the excavator or crane and lifting chains while the hydraulic rams are retracted.
- Backfill the excavation in adequately compacted layers to the underside of the next frame level.
- Remove the next frame level and continue this sequence up to ground level.
- Extract the trench sheets and reinstate the ground.
Please ensure all legs are fully retracted prior to collection.
Residual Risks
The following residual risks must be addressed in the Contractor's RAMS:
- Locate all potential services prior to excavation in accordance with NRSWA Regulations.
- The excavation may be classified as a confined space. The Contractor must assess this risk and provide suitable gas detection and rescue equipment where appropriate.
- The Contractor should always adequately consider the surrounding environment and account for adjacent structures, slopes, roads etc.
- Additional or independent edge protection may be required during the installation.
Safe Usage Checklist
- Ensure an adequate Lift Plan is incorporated into the method statement (by Contractor) and pay close attention to the weights of individual legs (see full specifications) and whole frame levels.
- Carefully inspect all components and hydraulics prior to use. Contact SEL for advice where damaged components are found.
- Ensure all operatives are Trained & Competent and have been briefed on the requirements of the Temporary Works Design where necessary.
- Install suitable edge protection, access system and Davit system where required.
- Ensure appropriate vertical support is provided to the legs during installation and removal.
- Allow a minimum of 100mm extension on the rams to enable retraction when removing the equipment.
- Don't enter an excavation before adequate shoring is in place.
- Don't use hanging chains for lifting.
- Don't use faulty or damaged equipment.
Edge Protection & Access
Please contact Site Equipment for info on our full range of Access & Edge Protection accessories.