Aluminium Waler Frame System Installation Guide

This is a step-by-step safe use guide covering how to assemble, install, and extract the Aluminium Waler Frame System, SEL's lightweight alloy waling frame for bracing trench sheets in utility and drainage trenches. Once the hydraulic struts are pinned to length, bolted between two waler rails on timber bearers, and pumped out to size, each frame level is lowered into position using an excavator or crane and a 4-leg chain sling for either dig-and-push or pre-driven sheet installation.

Key Considerations

Required Plant & Lifting Equipment
Excavator or crane · 4-leg chain sling · hydraulic pump
Component Weights
77kg (1.50m frame) to 168kg (5.00m frame)
Working Limits
1.50m–5.00m rail length · 0.50m–2.00m trench width · up to 80kN/m
Installation Methods
Dig & push (with dummy frames) or pre-driven sheets

Installation Sequence

Step 1: Assemble the Hydraulic Struts to Length

Exploded view of a waler strut: hydraulic strut foot, 500-820mm hydraulic ram, extension, connector, second extension and strut foot, joined by 20mm pins and R-clips, with a 10mm bolt and nut at each foot

Assemble each Waler Strut to match the required trench width by pinning tubular extension units onto the 500–820mm Hydraulic Ram (joining two extensions with a central connector where required) and fitting the opposite Strut Foot, locking every joint with a 20Ø Pin & R-Clip.

Step 2: Bolt the Struts Between the Aluminium Waler Rails

Two aluminium waler rails on timber bearers, with two waler struts and their bolts positioned across one rail ready to be connected

Lay two Aluminium Waler rails flat on suitable timber bearers on level ground. Position the assembled Waler Struts across the rails—using two struts on rails up to 3.0m long and three struts on 3.5m to 5.0m rails—and bolt each strut foot vertically through the rail flange using an M10 Bolt & Nut (see a ), ensuring the struts are set inwards from the rail ends at the correct spacing (see Waler Strut Arrangement).

If preferred—or where site access is restricted—the rails and struts can be assembled directly within the excavation at the level specified in the Temporary Works Design by following Steps 1–3 inside the trench.

Step 3: Connect the Hydraulic Pump and Extend the Frame

The assembled waler frame on timber bearers, with arrows showing the rails being pumped outwards

Check that the hydraulic pump tank is three-quarters full of shoring fluid. Connect the single hydraulic hose to the female coupling on the pump and attach the other end to the male connector on each Hydraulic Ram (see a ). Open the isolation valves, pump out the hydraulic rams to the required trench width (allowing at least 100mm of ram extension so the struts can later be retracted for removal), and close the lock-off valves to hold pressure.

Attach the hooks of a 4-leg chain sling through the four lifting points mounted on the waler rails.

Step 4: Excavate the Starter Pit and Lift In Two Frame Levels

Frame F1 and Temporary Frame A laid on timber bearers in a shallow excavated pit

Steps 4–8 describe the 'Dig & Push' installation method for an excavation with two permanent frame levels (Frame F1 upper and Frame F2 lower). For pre-driven sheets or three or more frame levels, see Alternative Installation Methods and Removal.

Locate all underground services in accordance with NRSWA regulations, then excavate a shallow starter pit down to the underside of the upper Frame F1 level (using a stepped or battered edge if required). Using an excavator or crane and a certified 4-leg chain sling, lift two assembled frame levels—permanent Frame F1 at the bottom with Temporary Frame A above it—into the shallow pit and seat them on timber bearers.

Step 5: Pitch and Push the Trench Sheets

Sheets pushed in along the two frame levels in the shallow pit

Using the two waler frames as an internal guide, pitch trench sheets along the outside of the waler rails and push them down using the excavator bucket and the correct driving cap until refusal, or to approximately half the final excavation depth. Hook the frame restraint chains onto the tops of the trench sheets.

Shorter trench sheets may be used temporarily to leave a digging window for the excavator if required.

Step 6: Excavate to Mid-Depth and Install Temporary Frame B

Frame F1 at the top of the sheets, with Temporary Frame B installed below it

Excavate inside the sheets down to the midpoint between the final levels of upper Frame F1 and lower Frame F2. Install a 'dummy' Temporary Frame B at this midpoint to restrain the bottom of the trench sheets before digging deeper. Lower Temporary Frame B partially retracted on a 4-leg chain sling and pump it out against the sheets in the trench (or assemble it inside the trench if clearance is restricted).

Once Temporary Frame B is pressurised and locked off, lift out Temporary Frame A from above Frame F1.

Step 7: Excavate to Lower Frame Level and Install Frame F2

View into the excavation showing Frame F1 at the top, Temporary Frame B in the middle and Frame F2 at the bottom, braced against the sheets

Continue excavating and incrementally pushing the trench sheets down until you reach the underside of the lower Frame F2 level.

Lower permanent Frame F2 into position on a 4-leg chain sling, pump its hydraulic struts out against the sheets, close the lock-off valves, and hook on its vertical restraint chains.

Once Frame F2 is installed, retract and remove Temporary Frame B from above it, then continue digging and pushing the sheets down to the final formation level (installing additional frame levels where required).

Step 8: Push Sheets to Final Level and Fit Edge Protection

The completed excavation with the sheets at their final level, the waler frames in place and edge protection along the top of both sides

Ensure all trench sheets are pushed down to their final design level—normally the formation level, unless a sheet toe-in below formation is specified in the Temporary Works Design.

Fit a suitable edge protection and ladder access system along the top of the excavation.

To extract the system, carry out this procedure in reverse—reinstalling the temporary frame levels as required while backfilling and compacting in stages so the sheets remain supported throughout removal.

Alternative Installation Methods and Removal

Alternative Installation: Pre-Driven Sheets

Use the pre-driven method when ground conditions are too firm or dense to push the trench sheets down with an excavator bucket, or where the Temporary Works Design requires full sheet toe-in before excavation begins. Instead of pushing the sheets down in stages as you dig, drive all sheets to full depth first using a driving cap or Excavator Mounted Vibrator (EMV), then excavate and brace from the top down:

  1. Pre-drive all trench sheets to the final toe level specified in the Temporary Works Design using suitable plant.
  2. Excavate down to the underside of the upper Frame F1.
  3. Install and pressurise Frame F1 at the level specified in the Temporary Works Design.
  4. Excavate down to the underside of the lower Frame F2.
  5. Install and pressurise Frame F2 at the level specified in the Temporary Works Design.
  6. Excavate down to the final formation level.
  7. Once the permanent works are installed, backfill and compact the excavation to the underside of each frame prior to retracting and removing it.

Dig & Push Installation with Three or More Frame Levels

Where three or more permanent frames are required, repeat Step 7 (Installing Frame F2) using additional temporary frame levels so the bottom of the trench sheets is restrained at every stage.

Excessive sheet cantilever below the lowest frame must be avoided.

Please ensure all struts are fully retracted prior to collection.

Waler Strut Arrangement

Ensure that the Waler Struts are positioned inset from the ends of the rails (facing inwards).

For two-strut arrangements (waler rails up to 3.0m long), the centre-to-centre spacing between the struts is:

Strut centres = Rail length − 0.72m.

For three-strut arrangements (3.5m to 5.0m waler rails), place the third strut centrally between the outer struts.

Side-by-side plan diagram showing correct inward-facing waler struts versus incorrect outward-facing struts

Residual Risks

The following residual risks must be addressed in the Contractor's RAMS:

  1. Locate all potential services prior to excavation in accordance with NRSWA Regulations.
  2. The excavation may be classified as a confined space. The Contractor must assess this risk and provide suitable gas detection and rescue equipment where appropriate.
  3. The Contractor should always adequately consider the surrounding environment and account for adjacent structures, slopes, roads etc.
  4. Additional or independent edge protection may be required during the installation.

Safe Usage Checklist

  • Ensure an adequate Lift Plan is incorporated into the method statement (by Contractor) and pay close attention to the weights of the Waler Frames (see full specifications).
  • Carefully inspect all components and hydraulics prior to use. Contact SEL for advice where damaged components are found.
  • Ensure all operatives are Trained & Competent and have been briefed on the requirements of the Temporary Works Design where necessary.
  • Install suitable edge protection, access system and Davit system where required.
  • Ensure appropriate vertical support is provided to the struts during installation and removal.
  • Allow a minimum of 100mm extension on the rams to enable retraction when removing the equipment.
  • Don't enter an excavation before adequate shoring is in place.
  • Don't use hanging chains for lifting.
  • Don't use faulty or damaged equipment.

Installing with Additional Equipment

End Bearer Rails

End Bearer Rails (available in three sizes) fit into the ends of the Aluminium Waler rails and are secured using a 14Øx150mm Long Pin & R-Clip and a 20Øx125mm Long Pin & R-Clip.

Close-up of an end bearer rail fitted into the end of a waler rail, labelled with the 14mm by 150mm long pin and R-clip, the 20mm by 125mm long pin and R-clip, and the end bearer rail in three sizes

Edge Protection and Access

Please contact Site Equipment for info on our full range of Access & Edge Protection accessories.

Common Questions

How do you calculate the strut spacing on an Aluminium Waler Frame?
Ensure that the waler struts are arranged facing inwards. For two-strut arrangements (up to 3.0m waler rails), the strut centres equal the rail length minus 0.72m. For three-strut arrangements (3.50m to 5.00m waler rails), place the third strut centrally.
What trench widths and rail lengths can an Aluminium Waler Frame support?
Aluminium Waler rails are available in seven lengths from 1.50m up to 5.00m. Using modular pin-on strut extensions, 1.50m to 2.50m frames support trench widths from 0.50m to 2.00m, while 3.00m to 5.00m frames support trench widths from 0.50m to 1.80m.
How much does an assembled Aluminium Waler Frame weigh?
Complete assembled Aluminium Waler Frames weigh 77kg (1.50m), 88kg (2.00m), 99kg (2.50m), and 110kg (3.00m) for two-strut frames, and 143kg (3.50m), 154kg (4.00m), and 168kg (5.00m) for three-strut frames. Because the alloy rails weigh 11kg/m and maximum-length struts weigh 22kg each, components can also be assembled inside the excavation where preferred.
How are the hydraulic struts connected to the Aluminium Waler rails?
Each strut is built to length by pinning tubular extensions to the 500–820mm hydraulic ram using 20mm pins and R-clips. The two strut feet then seat inside the C-channels of the opposing Aluminium Waler rails and bolt vertically through the rail flanges using M10 bolts and nuts.
How much ram extension is required when installing an Aluminium Waler Frame?
You must allow a minimum of 100mm extension on the hydraulic rams during installation to enable retraction when removing the equipment. All struts must be fully retracted prior to off-hire collection.
How are End Bearer Rails connected to an Aluminium Waler Frame?
End Bearer Rails (available in three sizes) fit into the ends of the Aluminium Waler rails and are secured using a 14mm x 150mm long pin and R-clip and a 20mm x 125mm long pin and R-clip.

We can help with your next project.

Our team is friendly, knowledgeable and ready to consult. We offer no-obligation site visits, fast delivery and competitive rates. Simply fill in the form and we'll be in touch.

You can also give us a call at any time.